Customer: Crown Castle - Disney

Location: Anaheim, CA

Product: Maxi-Mod 3056

Size: (2) 30 x 56 + central corridor: 66 X 56 Total

Delivery Method: Design Build

  • Wireless co-location facility for all carriers at Disneyland. ™©®
  • Centralized corridor providing access to five secured suites and common Telco and power rooms.
  • Fast-track design building project with expedited delivery schedule. The carriers were operational on schedule.
  • 2000A main electrical service; three generators with each suite having a least one dedicated electrical distribution panel.
  • Redundant HVAC; FM200 fire protection system and earthquake designed to meet California codes.

 